Bury ST Edmunds, Suffolk
Concrete pad installation for new waste compactor
Our team constructed the shuttering, reinforcement and subsequent concrete pour to create a new steel reinforced concrete base ready for our client to install their new waste compactor.
Services delivered
- Steel reinforced concrete
- Shuttering
- Excavation
- Armco barrier installation
Challenge
The existing ground from one side to the other was on an incline of around 300mm. The existing concrete had to be cut and broken out to construct new shuttering to ensure the new concrete pad was level with all the required falls needed for surface water drainage.
Delivery
Works were completed over a 2 week window ensuring minimum disruption to the busy loading bay next to the location of the new concrete pad.